We're changing out two elevators at a ethanol plant this week. huge elevators. 25,000 BPH 200' Discharge height. We're running our 190 and the 165. One crew on each of the legs. We started last Thursday with demo. Demo was done by Saturday afternoon. Started stacking the new ones Sunday morning. Set the head sections Monday afternoon. Today, Tuesday, setting the top drums, drives and motors. Planned to pull the belts in tomorrow but weather will be a factor. We should be operational by this weekend.
The 60 ton is just now repaired and operational. Setting HVAC units with it directly.
The 65 T is headed to a job.
Got another 65 ordered. Expect it to be delivered May/June.
100T has a windshield busted out. Don't ask.
Boom truck is broke.
That will be 7 cranes. We have only 4 operators.