• Thank you for visiting HeavyEquipmentForums.com! Our objective is to provide industry professionals a place to gather to exchange questions, answers and ideas. We welcome you to register using the "Register" icon at the top of the page. We'd appreciate any help you can offer in spreading the word of our new site. The more members that join, the bigger resource for all to enjoy. Thank you!

Rule of thumb for me ?

wingnut

Well-Known Member
Joined
Nov 24, 2008
Messages
100
Location
Hubbard Texas
Occupation
owner of a small sand gravel backhoe and dozer ser
When you have a job to tear down a structure such as a house , shed , barn , or for that mater any standing structure , How should a price for the job be priced ?
Is it normaly priced by the hour , size of the structure , or what ?
I am thinking of adding demo to my business but before I just jump in I thought it would be a good idea to ask pros. like yourselfs so I wont hurt myself or a customer . Can you tell me , What is a good rule of thumb I can go by and be safe . Thanks in advance , Wingnut
 

Squizzy246B

Administrator
Joined
Sep 9, 2005
Messages
3,388
Location
Perth, Western Australia
Occupation
Digger Driver
Wingnut, I used to do some demo but I got out....its all about your dumping fees. The quantity estimating comes with experience. I don't do any house demolition anymore....well...cept occaisionally when I reverse up too far in the loader:eek:..but the big demo mobs have their private tipping arrangements and I found it too hard to compete.

A wise old man of demo once told me that to estimate a house demolition walk around the house and imagine if the walls were all pushed inwards so it was a big pile of waste (like a pyramid). Calculate the volume and add 20% for the founds.

Around here, size matters. The big mobs come with nothing less than a 30 to 35 tonne excavator. Four bedroom double brick & tile houses disappear in 3-4 hours.

Also, be very careful with asbestos.
Things like carpets left in the house will bulk up your trucks.
 

CM1995

Administrator
Joined
Jan 21, 2007
Messages
13,379
Location
Alabama
Occupation
Running what I brung and taking what I win
Squizzy hit the nail on the head, demo is mostly about trucking and disposal.
Getting the structure down is the easy and fun part, hauling all the debris out profitably is the tricky part. I mainly do small structures like houses, sheds, etc so the advice below pertains to that type of structure. Safety is also paramount in any demo project and changes due to the type, location and materials involved. Definetely check into your local/state asbestos and demolition rules prior to pricing any job. The asbestos that we run into on residential demo is usually in the old siding ( I don't do abatement). In AL any commercial structure has to have an inspection and clean air permit from the state Environmental Department, it is not required on residential but the asbestos rules still apply.

First question - How does your local landfill(s) or hauling company(s) charge for disposal, by the ton or CY? That is very important, if they charge by the CY then it makes your estimating easier. If they charge by the ton then you have many more variables. What is the price per ton/CY for disposal and what do the hauling companies charge for a 30CY can in your area? Do the hauling companies charge a flat rate per box or haul+rental+tonnage? If you are going to use hauling companies you can negotiate a better rate for demo since the box will turn quickly - IE drop the box, load it out in 15-20 mins and it's gone. In the roll-off business you want your boxes turning quickly as opposed to sitting on a job for a month. The box only makes money when it is either being dumped or being delivered.

In my area all the landfills charge by the ton. We have 10 or so but only haul regularly to 4. The reason why I say paying by the ton has more variables is this:

I bid a burned out 900SF house to demo. The windows were boarded up and I could only see the living room through an opening - I was too lazy to take down the plywood and go inside, which turned out to be a big mistake. The rear bedroom and kitchen was not damaged by the fire and was filled with personal items to boot. Once I started in tearing down the house I found alot of wet clothes, books, kitchen items etc. This increased my tonnage and of course I bid the job hard. I ended up with more volume and tonnage due to the wet contents.

If you are paying by the ton or CY you will want to seperate as much concrete, brick, asphalt and other "inert" materials to be disposed of seperately. Around these parts these types of items are not regulated waste and can be used as beneficial fill. I have a place we haul this type material to and of course no tip fee.

Will you be hauling the debris yourself or contract out? I am a partner in a roll-off company and also have 1 dumptruck. When I do demo I plan which route and landfill to go to and incorporate that into my estimate (Google Earth works very well for this). I pay my roll-off company a set hauling fee and I pay the tip bill directly. I am able to save some money, the roll-off company makes money but the responsibiliy to acurrately estimate the tonnage is still on me.

Having control of the roll-off's coming in and out makes a big difference on the performance and bottom line of the project. I have the luxury of pulling an extra truck in whenever I need it to keep the job going smoothly during the load out stage. This is important since a profitable demo job is about speed and efficiency - get in and get out.

The Holy Grail of demo is how to estimate it. I use historical costs to estimate a SF cost plus the variables of contents inside, condition of structure (partially burned, intact, etc), hauling distance, amount of inert materials, access to the site and the time I think it will take to complete the job.

Then you have the different materials you will be working with that will either break/crunch up easily or not so easily. 3/4" plywood subfoor is a pain and will take up volume in a can/truck. OSB will break up easier and if it is an old structure with 2x decking/subflooring then you can get a tighter packed can. Then you just have the variables of "hidden" items. Like the front porch that had wood flooring but turned out to have reinforced 6" concrete underneath it.:Banghead

With demo you will win some and loose some. With experience and historical job cost numbers you will be able to get closer on every job.
 

wingnut

Well-Known Member
Joined
Nov 24, 2008
Messages
100
Location
Hubbard Texas
Occupation
owner of a small sand gravel backhoe and dozer ser
Thanks guys , I didnt realize accutally how much was involved in demolition , I am glad I asked . This gives me alot to think about and concider . I am not scared of working on trying to build this small business up , But looks like Ive got alot of research to do on this end as far as what yall have talked about in the previous posts before I get my feet wet .
If yall can think of anything else , I would be greatful . I dont want to bite of more than I can chew . Thanks again , Wingnut
 