fensoncont.
Senior Member
I was wondering if anyone here works on a piling crew or ever has? I'm new to this and trying to get a good idea on this type of work. What I'm working with right now is 12, 14, and 16" CIP Concrete Piles. Some are 20' deep and some get up to 50' deep. There is also some Steel Piles as well, and from what I understand steel piles don't consume as much time. I'm guessing that piling production is measured in vertical feet? On my own thinking I can guess anywhere from 3-5 laborers around on site performing general help? Assuming ideal conditions, including the soil what is good production for pile driving in steel and concrete? Thanks in advance for your help!