I have a customer that is building a new yard. He has a 10 acre lot that he wants covered in with 6" of road base or other suitable structural fill.
I figured about 10,500 CY.
The pit is 14 miles from the job site. How many trucks (either end dump, belly dump or tandem) would you use?
I am going to have my grader and a roller out there to spread everything.