• Thank you for visiting HeavyEquipmentForums.com! Our objective is to provide industry professionals a place to gather to exchange questions, answers and ideas. We welcome you to register using the "Register" icon at the top of the page. We'd appreciate any help you can offer in spreading the word of our new site. The more members that join, the bigger resource for all to enjoy. Thank you!

Digging around utilities again

xcavate77

Active Member
Joined
Dec 18, 2007
Messages
38
Location
Iowa
this got erased in the switch I'd like to see any similar pics from anyone else thanks
 

Attachments

  • Utility resize.JPG
    Utility resize.JPG
    79.5 KB · Views: 505

ForsytheBros.

Well-Known Member
Joined
Jan 1, 2007
Messages
100
Location
austin, texas
THAT looks nasty:notworthy

Q1: did you guys anticipate that bird's nest at bid? Did the owner/engineer? If unforseen on plans, how do you typically deal with this situation? Time +materials ? Extra days on the critical path?


Q2: Looks like a tough area to get shoring in. What was your method of excavation protection?
 

xcavate77

Active Member
Joined
Dec 18, 2007
Messages
38
Location
Iowa
A1: Some time was reflected in our bid, in areas like this we will call in locates before bid if there is any concern. Engineers/ Owners just say these situations are "incidental" to construction. Took approximately 6 additional hrs of crew time from what was anticipated.

A2: We used hydraulic shoring to get in between the utilities then a trench box for the remainder (8' X 24) we were digging with a 450 Deere and a 420 Cat around the lines with a hydro vac assisting.

Thanks for the inquiry
 