We are looking at bidding on a concrete tear out job and need a little help. The concrete is from the 1920s and its loaded with rebar and its 16 inches thick. It is a 16 inch slab 300 feet by 300 feet and then pillars 6 foot tall and then another 16 inch slab of the same size on top of that and then a poured concrete wall building with walls 6 inches thick 30 foot tall. We have a hammer on our kobelco sk300 and are thinking about getting a concrete pulverizer for our old cat 225. How hard is a concrete pulverizer on an excavator? We are hoping to use both machines rather than switching from hammer to pulverizer back and forth on the kobelco. We dont own a pulverizer yet and were looking for opinions on if it is worth it? Any other imput appreciated.