Ours is right at $19 and channge per ton for Inch Base, either bleding being done too hurriedly or poorly as getting more inch clean than base fines. Quarry running 24/7 for Data Center materials so expect fatigue and expedience affecting them.
New mat under Blue and remnant of third load stockpiled. Two full loads came up the drive from the highway ~18t a load


New mat under Blue and remnant of third load stockpiled. Two full loads came up the drive from the highway ~18t a load