crazycajun
Well-Known Member
I have to move 500,000 cu yards in 120 calender days. Average haul 800 ft. I will have 4 D400's being pulled by 2 quadtrac's and 2 independant 740's. I will be loading with a 385, 7.25yd bucket. 5-7 acre hole +- 35ft deep. i will just need to pile dirt in 3 specific locations, piles will be approx 20ft tall. i plan to run the trucks on top of the pile as i go up. Hoping to haul 10,000 yards/day What size dozer will i need to keep up with the trucks? I have 2 D6N's. Looking to aquire something that can handle this situation.