Thanks for the advice.
I tried a small independent lawyer at the start, and without going into too much detail, he didn’t really help at all and worsened the situation. I have reason to believe he may have been threatened to leave our case alone.
I’m looking at some other firms now but this part of it is all new to me. Others who dealt with same client have told me to prepare for a possible 10 year case before I get anything out of it.
I did add good mark-up to the project when we bid it. Being a smaller company I don’t have near the overhead of some of the bigger guys. I’m aware of my costs and theres and often try to match just under their pricing and take the in between which is up in that 20-30% mark.
Quantities I have no issue with, I got paid for about 1/3 extra what we bid on. Just got no relief as far as timeline extension to allow for the extra, no force account work (there was a lot) and they never pro-rated the lump sum items to reflect the increase in work.
We‘ve been through the full dispute process on 3 disputes now. Each one they took no fault in the situation, basically sent me a letter stating so every time it was their turn to respond, and they forced me to sign an agreement waiving the first two disputes or they would have charged about an additional $50,000 in LD’s for a period of time in the spring when the min rep wanted us to start but I told him I wanted to start later because the ground water table was too high. And the third dispute they were late responding to one of the notices, I called them on it and they carried the dispute on. I was late responding to one of their notices and they threw the dispute out. So no chance of easy mediation there.
Very bad situation but I do feel I have some things going for me on this one. The waiver I signed to drop the first two disputes was another one. I was looking at it today and they broke contract on that one. I asked for a supplemental agreement for a change of work order as I am entitled to in the contract, I got an improper response back stating they would give me 1 day extension and to charge force account. I disagreed and asked for the change of work order. The following spring, the supplemental agreement to drop both disputes and a 1 day timeline extension is what they came up with and had me sign.
It they were extras, did you get any sort of change order or PO for them? If not you're pretty much screwed. And even if you got it in writing they agreed to the extras, unless they were done in a way stipulated in the contract for extras you're pretty much screwed for getting paid for them too. With any big company I would never ever touch a extra I expect to be paid for until I have a PO in writing.
Were these dispute processes just minor one's over the course of the project?
Honestly it sounds like a mess and it won't be cheap for lawyers to sort out. Generally speaking if the start time is in the contract and you refuse it's on you, even if you have a reason like high water table, you can warn them it's not a good idea but if they want you there, you will be screwed for the delays if you don't.
If there is anyway to do it, I would probably just go binding mediation route.