1. Thank you for visiting HeavyEquipmentForums.com! Our objective is to provide industry professionals a place to gather to exchange questions, answers and ideas. We welcome you to register using the "Register" icon at the top of the page. We'd appreciate any help you can offer in spreading the word of our new site. The more members that join, the bigger resource for all to enjoy. Thank you!
  2. ALL NEW MEMBERS READ THIS FIRST!! Thank you for joining Heavy Equipment Forums! If you are new to forums we communicate with "Threads", please search our threads to see if your topic may have already been answered and if not then click "Post New Thread" in the appropriate forum. This will allow all of our members to see your question and give you the best chance to be answered. After you've made a number of posts you will graduate to Full Member status where you'll see a few more privileges. Following these guidelines will help make this the best resource for heavy equipment on the net. Thanks for joining us and I hope you enjoy your stay!!

Crane lifting a Crane (youtube video)

Discussion in 'Cranes' started by colson04, Jul 2, 2020.

  1. colson04

    colson04 Senior Member

    Joined:
    Apr 11, 2016
    Messages:
    1,143
    Location:
    Delton, Michigan
    Up way too early with my youngest so we started youtubing to keep her quiet why everyone else slept. Stumbled onto this neat video.

    Quick question for those in the know: Did they leave the extra rear counterweights off for clearance with the canal berm, or could they have raised them up higher to clear the berm while doing the initial pick? I can see it wasn't necessary to have them on for the entire pick, but I was wondering if that was standard practice to take them on/off during a pick like this?

     
    muzy, DMiller, Pixie and 1 other person like this.
  2. kshansen

    kshansen Senior Member

    Joined:
    Mar 11, 2012
    Messages:
    9,582
    Occupation:
    Retired Mechanic in Stone Quarry
    Location:
    Central New York, USA
    Not really sure but guessing that they only needed them on for when they needed to boom down. Maybe if they were on too soon they would have made the weight too much on the back to be able to swing?

    Maybe Crane operator will see this and give a better explanation, I know what I'm thinking but putting it into words just doesn't come out right!

    Something along the line of keeping things in balance not too much counter weight and not too much load on boom end. Add a little at each side and no real stress in either area.
     
    DMiller likes this.
  3. John C.

    John C. Senior Member

    Joined:
    Jun 12, 2007
    Messages:
    9,979
    Occupation:
    Machinery & Equipment Appraiser
    Location:
    Northwest
    What little I've seen with the big crawlers and wheel horses or trays was that they were generally used when the main booms were picked up or set down. As far as the clearance on the berm goes what I've seen was that the trays were only picked up a few feet off the ground as the tray moves in an arc as it moves higher which changes the load center the higher the tray is lifted. Maybe there is a limit on how high the tray can be lifted.
     
    DMiller likes this.
  4. Tugger2

    Tugger2 Senior Member

    Joined:
    Mar 22, 2018
    Messages:
    964
    Location:
    British Columbia
    That stack needs to hang on its own for the crane to swing ,no wheels or tracks to help carry it when theres no load on the crane. Id say boomed up with no load that machine might be close to tipping backwards . Just my 2csworth. Pretty interesting way across though , slicker than bringing in a sectional barge.
     
    DMiller and John C. like this.
  5. Welder Dave

    Welder Dave Senior Member

    Joined:
    Oct 12, 2014
    Messages:
    6,384
    Location:
    Canada
    I think the crane could swing with the additional counterweight as long as the boom was laid down some. Near the end of the video it looks the there is extra counterweights on top of the extension at the back of the crane. With the boom up I agree the crane might go over backwards with no weight on the hook. I think the counterweight was attached before the boom was lowered but the boom may have been lowered slightly before the counterweight was attached. Having all the counterweight on and turning empty might put lots of unequal stress on the slewing ring and rollers.

    I had a woman do my taxes years ago that her family had an older crawler crane they were using as dragline. It wasn't a really large one. They were having it moved and told the driver not to go over 35 MPH to avoid bouncing. They were following behind but stopped for a couple minutes to pick up some food for everybody. They were wondering why it took so long to catch back up to the truck. When they did the truck was going 65 MPH! They chewed the driver out but it didn't do much good. I think she said it cost over 15K to have all the rollers in the slewing ring replaced. It was the first and last time they ever used that trucking company, who were supposedly specialists in moving equipment like this.
     
  6. kshansen

    kshansen Senior Member

    Joined:
    Mar 11, 2012
    Messages:
    9,582
    Occupation:
    Retired Mechanic in Stone Quarry
    Location:
    Central New York, USA
    Some jerks think if a machine will do that 65 MPH then that is what they need to do!
     
    DMiller likes this.
  7. Tugger2

    Tugger2 Senior Member

    Joined:
    Mar 22, 2018
    Messages:
    964
    Location:
    British Columbia
    I wonder what kind of bed they were running to do damage like that ? Never had a problem with a bed on airbags.
    At 200.00/HR i like to see my lowbed guy pedal to the metal when we are moving.
     
    DMiller likes this.
  8. Knepptune

    Knepptune Senior Member

    Joined:
    Nov 22, 2012
    Messages:
    706
    Location:
    Indiana
    240’ of boom isn’t much on an 18000.

    Spec sheet Shows you can put 320’ of main in the crane without the maxer. That means the crane has will pick 320’ of boom off the ground without the maxer attachment.

    Beast off a crane. 528k of counterweight on the upper and another measly 320k of carbody weights. That’s without maxer.


    To put the maxer in it you can only hang 492k counterweight on the upper but it gives you the option to add 860k counterweight on either a wagon or tray. They have the tray on that crane. The wagon has wheels to allow the crane to slew with floating the tray. I’m gonna say it would take one heck of a load to float a tray with 860k counterweight.

    All that to say that an empty hook with 240’ of boom is not gonna float that tray. They simply couldn’t swing without a load on the crane if the tray was attached.
     
    colson04 likes this.
  9. Welder Dave

    Welder Dave Senior Member

    Joined:
    Oct 12, 2014
    Messages:
    6,384
    Location:
    Canada
    If the customer paying the bill says to not drive over 35 MPH, you should respect that, especially if getting paid by the hour. Maybe they know their machine better than the truck driver. It makes sense excessive bouncing could cause damage. The average speed when they moved the 820 tonne vessel was around 2 MPH.
     
    DMiller and kshansen like this.
  10. crane operator

    crane operator Senior Member

    Joined:
    Mar 27, 2009
    Messages:
    5,572
    Location:
    sw missouri
    The crane with tray on, is essentially like two cranes, with two lattice booms. One boom is lifting the load, one boom is lifting the tray with all the extra weights. The crane they are lifting over the canal, had to be 1/2 way across the canal, before lifting the tray, in order to balance the load so to speak.

    When they have a wagon on, the extra weight can ride around on the wagon until they need it (have enough load to pick it up), but the berm makes it so they would have needed to be a lot further away to have room for the wagon, and the wagon would have to have mats also. It doesn't look like the best ground in the world they are working on either. So they took the easy way and just hung the weight when they needed it.

    Also- the video overstates the load weight of the crane a little. That AT may weigh that with all the weights on, but they lifted it across without all the counterweights on.
     
  11. Raildudes dad

    Raildudes dad Senior Member

    Joined:
    Dec 29, 2007
    Messages:
    400
    Location:
    Grand Rapids MI
    My guess is there was a cheaper alternative if the big girl wasn't already on site. My local crane guy (with the cranes around the US) told me he turned down a big windmill project in MI. He said they wanted him to cat his machine all over the wind farm on temporary roads. Said, nope, not putting all that wear on my undercarriage. And with the money he has he can do that.
     
    DMiller likes this.
  12. kshansen

    kshansen Senior Member

    Joined:
    Mar 11, 2012
    Messages:
    9,582
    Occupation:
    Retired Mechanic in Stone Quarry
    Location:
    Central New York, USA
    Must be I forgot to hit send last night on this one but here it is now!

    All I can say is if they requested the speed to be 35 mph and the guy hauling it, or his boss, had a problem with that request he should not have agreed to hauling the load.

    If I ask you to paint my car green and you try to give it back painted red then it's not my fault. Feel free to tell the customer why you don't want to do as he asks but as he is paying the bill he is now the boss!
     
    DMiller and Tugger2 like this.
  13. DMiller

    DMiller Senior Member

    Joined:
    Feb 22, 2010
    Messages:
    11,218
    Occupation:
    Almost Retired
    Location:
    Hermann, Missouri
    Saw similar at the Nuke lifting the Steam Generators with the 600 tonner, counterweight was on wheels ran on a timber mat track covered in steel plates until the load was lifted boom down, then the wheels did not touch as raised counter weight adding weight of load same time, the lift occurred boomed up and tires resumed rolling across mat structure.
     
    colson04 likes this.
  14. kshansen

    kshansen Senior Member

    Joined:
    Mar 11, 2012
    Messages:
    9,582
    Occupation:
    Retired Mechanic in Stone Quarry
    Location:
    Central New York, USA
    Sort of like adjusting the pivot point of a teeter-totter to adjust for different size kids!
     
    DMiller likes this.
  15. DMiller

    DMiller Senior Member

    Joined:
    Feb 22, 2010
    Messages:
    11,218
    Occupation:
    Almost Retired
    Location:
    Hermann, Missouri
    OSG & Turb 208.jpg was one VERY Large crane!!
     
    colson04 and Tugger2 like this.
  16. DMiller

    DMiller Senior Member

    Joined:
    Feb 22, 2010
    Messages:
    11,218
    Occupation:
    Almost Retired
    Location:
    Hermann, Missouri
    Took a massive Mani to assemble this monster.

    OSG & Turb 247.jpg

    They had issues, used Mammoet to lift a Truck crane to the platform for insertion into the Round Building, cut the lifting webbing FOUR Times before Safety had a vainer and made them regroup.
     