• Thank you for visiting HeavyEquipmentForums.com! Our objective is to provide industry professionals a place to gather to exchange questions, answers and ideas. We welcome you to register using the "Register" icon at the top of the page. We'd appreciate any help you can offer in spreading the word of our new site. The more members that join, the bigger resource for all to enjoy. Thank you!

quick questionnaire for utility contractors

dayexco

Senior Member
Joined
May 21, 2005
Messages
1,224
Location
south dakota
those of you in site utilities, or concrete work, please take the time to answer these questions. if you would, quote this post, and answer behind each question. thanks in advance.

in south dakota, our typical drop inlets/catch basins (2' x 3') inside, (3' x 4') outside or (3' x 4') inside, and (4' x 5') outside. my travels around the united states, i've seen tens of thousands of these.

#1. do you cast the inlets in place?

#2. do you buy your inlets precast from an outside vendor?

#3. do you precast at your own shop site and haul to site and install?

#4. those of you that cast in place, how much would you estimate your forming costs are? DO NOT include the cost of the concrete, or rebar. PLEASE INCLUDE your labor, plywood, screws, nails, dump fees for used/damaged form plywood, etc. i'm just asking for an off the top of your head number here, please waste no time looking up this for me!

#5. after stripping the inlets, do you attempt to save any of the plywood, etc, or just throw away and start with new forming material.

#6 if you try to save it, what percentage roughly are you able to reuse?

thank you so very much for your time helping me with this!
 

dayexco

Senior Member
Joined
May 21, 2005
Messages
1,224
Location
south dakota
boy, i'd really appreciate the help with this. am working on a new product concept, and need the feedback.
 

CM1995

Administrator
Joined
Jan 21, 2007
Messages
13,373
Location
Alabama
Occupation
Running what I brung and taking what I win
Answers in bold below.

those of you in site utilities, or concrete work, please take the time to answer these questions. if you would, quote this post, and answer behind each question. thanks in advance.

in south dakota, our typical drop inlets/catch basins (2' x 3') inside, (3' x 4') outside or (3' x 4') inside, and (4' x 5') outside. my travels around the united states, i've seen tens of thousands of these.

#1. do you cast the inlets in place?

Yes, almost exclusively, although I have poured in place.

#2. do you buy your inlets precast from an outside vendor?

Yes. They can make custom boxes with weirs for detention/retention structures.

#3. do you precast at your own shop site and haul to site and install?

N/A

#4. those of you that cast in place, how much would you estimate your forming costs are? DO NOT include the cost of the concrete, or rebar. PLEASE INCLUDE your labor, plywood, screws, nails, dump fees for used/damaged form plywood, etc. i'm just asking for an off the top of your head number here, please waste no time looking up this for me!

Labor to pour bottom - 2 guys, 2 hours each. 4 hours @ $30 = $120
Labor to form a standard 3x4 box 4' deep - 2 guys, 8 hours each. 16 hours @$30 = $480
Labor to pour box - 2 guys, 2 hours each. 4 hours @$30 - $120.
Material - nails, screws, 2x4's and plywood. Rough material number $300.
Disposal - either put it in GC dumpster if available or haul back to shop and burn or burn on site if allowed.

#5. after stripping the inlets, do you attempt to save any of the plywood, etc, or just throw away and start with new forming material.

For the few I've done I did not save the material.

#6 if you try to save it, what percentage roughly are you able to reuse?

If we did more PIP inlets I would say at least 2 uses out of the 2x4's and maybe 2 uses out of the plywood. The used plywood can be cut up to make smaller forms

thank you so very much for your time helping me with this!

Hope this helps.
 

CM1995

Administrator
Joined
Jan 21, 2007
Messages
13,373
Location
Alabama
Occupation
Running what I brung and taking what I win
thank you VERY much, truly appreciated!!

No problem, I enjoy discussing job site topics.

There are more members who are also in the business. I remember seeing TD25C has some metal forms and pours structures out in the field.
 

td25c

Senior Member
Joined
Feb 14, 2009
Messages
5,250
Location
indiana
I remember seeing TD25C has some metal forms and pours structures out in the field.

You have a good memory CM .:)


My metal forms are for round structures . They are 4' inside diameter . Made out of 14 gauge sheet steel that bolt together at the seems . Pretty easy & cost effective to set up . The drawback is took 3 pours to complete the man hole .

I actually poured the lids & base sections at the concrete plant . Plant did not offer any precast products so there was no conflict . Plant manager let us set up the forms beside the batch plant .

We then loaded them on lowboy & rolled them to the job and set them off . Next called truck to pour the inverts " channels" in the bottom .

Then set the base in the hole & tie in pipe .In the third picture can see the precast lid setting off to the side .

Set forms on top of base unit and finish pouring wall to desired height .

Always liked messing around with precast , most of the time on common items it's more cost effective to just pick up the phone & order it from the precast supplier .

But once in awhile on odd items I will set up forms on site & call a truck to fill it . Then set it in the hole .

This was a weir that we poured on site in a parking lot using plywood & "gates " tie system .

http://www.heavytruckforums.com/showthread.php?263-Some-Holmes-750-action&p=1862&viewfull=1#post1862
 

Attachments

  • Man Hole 001.jpg
    Man Hole 001.jpg
    94.8 KB · Views: 91
  • Set Man Hole 001.jpg
    Set Man Hole 001.jpg
    159.2 KB · Views: 90
  • Pour Man Hole 1 001.jpg
    Pour Man Hole 1 001.jpg
    121.3 KB · Views: 90

redneckracin

Senior Member
Joined
May 19, 2010
Messages
574
Location
Western PA
Occupation
Civil Engineer
There are several plants in PA that cast all manner of inlets because PennDot has specs that have to be met for them. I can't recall the last time I saw one cast in place but I'm sure it happens. the only problem would be that it would have to be designed by an engineer and stamped. For private work, I'm not much help other than the precast are pretty economical and those are usually the types that get spec'd.
 
Top