• Thank you for visiting HeavyEquipmentForums.com! Our objective is to provide industry professionals a place to gather to exchange questions, answers and ideas. We welcome you to register using the "Register" icon at the top of the page. We'd appreciate any help you can offer in spreading the word of our new site. The more members that join, the bigger resource for all to enjoy. Thank you!

Demag tilt-up crane

skyking1

Senior Member
Joined
Nov 3, 2020
Messages
7,662
Location
washington
Near my house, check out this Demag looks built for tilt-ups. I did not get close enough for a model.
PXL-20210407-222106018.jpg
 

AzIron

Senior Member
Joined
Jun 14, 2016
Messages
1,547
Location
Az
Down here its typically done with a crawler cranes around the outside of the building I have never seen them set up on the slab that said we dont have that kind of rain
 

CM1995

Administrator
Joined
Jan 21, 2007
Messages
13,375
Location
Alabama
Occupation
Running what I brung and taking what I win
Down here its typically done with a crawler cranes around the outside of the building I have never seen them set up on the slab that said we dont have that kind of rain

First thing I thought when I saw that pic is that's one hell of a slab to have that much weight on it. I wonder what the 7 day breaks for that slab broke at?

We've only worked on one tilt up project and I've seen many here where all the cranes are set up outside, off the slab raising the panels whether the crane is a crawler or mobile.
 

AzIron

Senior Member
Joined
Jun 14, 2016
Messages
1,547
Location
Az
Down here most guys dont pour the floor till after the panels are up and the roof is on makes for a really fast schedule to dig footings then the plumbers and sparkys have at it while the panels cure on waste slabs outside the building panels go up roof goes on then the floor is poured but it varries by contractor to
 

CM1995

Administrator
Joined
Jan 21, 2007
Messages
13,375
Location
Alabama
Occupation
Running what I brung and taking what I win
AZ I've seen it done over here that way as well. Back in the early 2000's we were working on a condo project next to an architects office under construction. GC poured thin casting beds for the 2 story tilt up panels on the outside of the slab.
 

Tones

Senior Member
Joined
Mar 15, 2009
Messages
3,085
Location
Ubique
Occupation
Ex land clearing contractor, part-time retired
Originally when tilt panels invented the floor was poured first then the panels poured on that. It saved a heap on transport costs.
 

skyking1

Senior Member
Joined
Nov 3, 2020
Messages
7,662
Location
washington
Just down the road they did the crawler on the outside method.
PXL_20210222_231104817.MP.jpg
That crane with the cable stays and 8 axles is good for pick and carry, I imagine there was some of that in the corners.
When you pour the final slab inside then you have closure pours all the way around. I have seen electrical go into those closures, but tilting up from outside with a crawler lets you do a single inside pour.
 

AzIron

Senior Member
Joined
Jun 14, 2016
Messages
1,547
Location
Az
A single pour on an average size tilt building here would be a tall order for finishers that said I have seen 2 laser screeds on the same pour I think that is more for redundancy tho

Those crawlers are a fast way to stand panels a half million square foot building can be stood up in less than a week with a good crew
 