oceanobob
Senior Member
Always wondered how I get from the classroom or the catalog to work on an existing pipe while using trench shoring. Now I get to know: have to go 7' down at the street shoulder to install a sewer lateral. The existing pipe (as observed in the manhole at the next intersection) is 8" clay. Locator says it is 6 to 8 feet down; manhole tape measuring and logical eyeballing indicates just shy of 7'. Soil is a sandy loam but low on the clay; yes, a hand dug hole will stand 5' deep.
*
Local shoring rental is either a shield or a box that can be lowered into the trench, or, pieces of thick plywood and hydraulic shoring jacks.
*
Excavation plan is to position the machine off and square to street and trench a nice square hole with the end near the tractor being a slope to facilitate the new 4" plastic pipe for the sewer lateral. At some point it will be necessary to enter the trench and explore the next depth with a shovel in order to locate the pipe; if not located, dig that next thin depth using the tractor, repeating this process until the pipe is located, hand dig around the pipe using the tractor to remove the spoils. That plan doesn't mention the shoring and the next section asks about that.
Here is my question: if the trench gets to 4' and then the shoring is installed, how does the additional digging proceed? Seems the space is kind of small for the bucket to enter and remove the soil. All the pictures shown in the trench safety classes and the catalog show a standing wall trench cut where there is no pipe, the shoring is then installed, then the pipe is magically installed and folks inside the trench with nice clean hardhats and clothes and new shovels happily working (if work means taking pictures of themselves).
If I get a shield or box we can lower it in the trench and then enter and look for the pipe, then remove it, dig a little etc. But that means the trench walls will have to stand and that may be asking a lot for this type of soil, especially when we get near the final depth. A slough off may occur under the asphalt of the road and a repair as well as a traffic plan will have to be enacted. Obviously a slough off not a good occurrence: to be avoided.
If I excavate to 4' then install the two sets of jacks per each sheet of plywood, digging with the tractor will be tedious if not impossible as the backhoe bucket is around 5' horizontal measured from teeth to ram and the spacing of the jacks will not accommodate this. I can also get some shoring items that are longer and these have horizontal whalers to allow the jacks to be spaced further apart.
The other point is once the shoring is installed with the jacks at the four feet or so depth, and if there is some trick to deepening the excavation, does one excavated quite a ways below the shoring in order to install the lower row? Seems unlikely - I am thinking the trench is dug and the lower row is installed then the upper. Which is ok as long as noone enters the trench.....but that is the rub: if we cant enter we cant find the pipe, if we shore then subsequent excavation is a challenge with the shoring in place. Rental inferred we could trench to 5', install shoring and then trench below the shoring for the additional 1 to 2 feet to access the existing pipe. If this is done, how to get that last bit of dirt out - one pail at a time? LOL.
Basically: how to dig a hole and enter to find an existing pipe with the goal of not damaging the pipe and not having a trench collapse. Thanks in advance.
*
Local shoring rental is either a shield or a box that can be lowered into the trench, or, pieces of thick plywood and hydraulic shoring jacks.
*
Excavation plan is to position the machine off and square to street and trench a nice square hole with the end near the tractor being a slope to facilitate the new 4" plastic pipe for the sewer lateral. At some point it will be necessary to enter the trench and explore the next depth with a shovel in order to locate the pipe; if not located, dig that next thin depth using the tractor, repeating this process until the pipe is located, hand dig around the pipe using the tractor to remove the spoils. That plan doesn't mention the shoring and the next section asks about that.
Here is my question: if the trench gets to 4' and then the shoring is installed, how does the additional digging proceed? Seems the space is kind of small for the bucket to enter and remove the soil. All the pictures shown in the trench safety classes and the catalog show a standing wall trench cut where there is no pipe, the shoring is then installed, then the pipe is magically installed and folks inside the trench with nice clean hardhats and clothes and new shovels happily working (if work means taking pictures of themselves).
If I get a shield or box we can lower it in the trench and then enter and look for the pipe, then remove it, dig a little etc. But that means the trench walls will have to stand and that may be asking a lot for this type of soil, especially when we get near the final depth. A slough off may occur under the asphalt of the road and a repair as well as a traffic plan will have to be enacted. Obviously a slough off not a good occurrence: to be avoided.
If I excavate to 4' then install the two sets of jacks per each sheet of plywood, digging with the tractor will be tedious if not impossible as the backhoe bucket is around 5' horizontal measured from teeth to ram and the spacing of the jacks will not accommodate this. I can also get some shoring items that are longer and these have horizontal whalers to allow the jacks to be spaced further apart.
The other point is once the shoring is installed with the jacks at the four feet or so depth, and if there is some trick to deepening the excavation, does one excavated quite a ways below the shoring in order to install the lower row? Seems unlikely - I am thinking the trench is dug and the lower row is installed then the upper. Which is ok as long as noone enters the trench.....but that is the rub: if we cant enter we cant find the pipe, if we shore then subsequent excavation is a challenge with the shoring in place. Rental inferred we could trench to 5', install shoring and then trench below the shoring for the additional 1 to 2 feet to access the existing pipe. If this is done, how to get that last bit of dirt out - one pail at a time? LOL.
Basically: how to dig a hole and enter to find an existing pipe with the goal of not damaging the pipe and not having a trench collapse. Thanks in advance.