Gillettex
New Member
Good evening,
I am currently bidding on a project that has the following criteria.
Topsoil stripping - 12,745 cyd
Cut - 8,758
Fill - 12,465
Loose Fill - 3,707
Topsoil Replace -3,645
There is room to cut in a borrow pit to get the 3707 yards of material, and I can backfill with topsoil to prevent extra export of topsoil. All "suitable" material is a brown clay and site is approximately 800x460 and the borrow pit is roughly 270' from one end of the site. The cut that I'll be excavating will not fill the far side from the pit and I will need to haul over and build that area up. Topsoil is to be stockpiled on site and then hauled off after replacing.
My questions is if we are planning on this site being wet due to spring (not a strict schedule but must be worked on starting late winter). What is the proper way to figure cubic yard pricing.
Do you charge the cut and fill seperately? Should it be different based on weather. Also what is going rates for something similar and what it out of line.
Thanks!
I am currently bidding on a project that has the following criteria.
Topsoil stripping - 12,745 cyd
Cut - 8,758
Fill - 12,465
Loose Fill - 3,707
Topsoil Replace -3,645
There is room to cut in a borrow pit to get the 3707 yards of material, and I can backfill with topsoil to prevent extra export of topsoil. All "suitable" material is a brown clay and site is approximately 800x460 and the borrow pit is roughly 270' from one end of the site. The cut that I'll be excavating will not fill the far side from the pit and I will need to haul over and build that area up. Topsoil is to be stockpiled on site and then hauled off after replacing.
My questions is if we are planning on this site being wet due to spring (not a strict schedule but must be worked on starting late winter). What is the proper way to figure cubic yard pricing.
Do you charge the cut and fill seperately? Should it be different based on weather. Also what is going rates for something similar and what it out of line.
Thanks!