View Full Version : Trenching Question?


fensoncont.
08-08-2007, 08:49 AM
Hey guys,

I am working on an estimate for a project and I had a question. The project involved laying a 16" PVC Waterline. The trench needs to be cut 6 ft. deep and 3 ft. wide. I'm estimating using a Vermeer T-655 or a T-658. The trench is going through natural clay. I am trying to figure out how many ft./hr. the trencher would trench. When using an excavator I can do the math to figure out how much it can cut in an hour, but I am new to figuring it with a trencher. Any help is appreciated!

dayexco
08-10-2007, 09:41 PM
321 feet per minute

fensoncont.
08-10-2007, 09:51 PM
Would that be ft./hr.?

surfer-joe
08-10-2007, 11:19 PM
Must have a D11 in front, and another one out back on that trencher......